Douglas Park

Development of Douglas Park:
Phase 1: BMX Track and 7-a-side football pitch with fencing/parking
Phase 2: Upgrade of play facilities/picnic benches
Total Cost circa £140,000
Hired Creetown Initiative as consultants
Planning Approval granted 26/08/15
Funding approved from:
Holywood Trust     £40,000 (for BMX and football pitch)
Robert Barr Trust   £10,000

A map outlining the proposed features in douglas park Newton Stewart

The Current Position

Adoption agreement secured from D&G Council.

Changing Places toilet has been built and handed over to DG Council.

The teen pod shelter has been built and all play equipment installed